Kaiyi — 4. MECHATRONICS SYSTEM

2) TEST PROCEDURE (1) Test 18: Check voltage between connector CN-88 (2) - GND. Disconnect connector CN-88 from power max solenoid valve. Starting switch ON. Check voltage as figure. SPEC : Starting switch ON : 24 ± 1V Starting switch OFF : 0V ① Power max switch ② ③ LH RCV-lever CN-88 Power max solenoid valve 1 2 1 2 Ground Multimeter 140L6MS123 (2) Test 19: Check resistance of the solenoid valve between CN-88 (1)-(2). Starting switch OFF. Disconnect connector CN-88 from power max solenoid valve. Check resistance as figure. SPEC : 15~35 Ω ① ② Power max switch ③ LH RCV-lever CN-88 Power max solenoid valve 1 2 1 2 Multimeter 140L6MS124 6-64