Testing Main relay Flash code: 2x long, 5x short Fault indication: Fault is not indicated by the EDC indicator lamp Fault path: Main relay Contact sticks or jams (does not open) Effect of fault: Under certain conditions, this fault may not be detected Function: The negative side of the relay coil is triggered by the EDC control unit via the control unit output pin 46. The main relay switch-off is delayed after the igni- tion is switched off (run-on). During the run-on phase, various processor functions are checked and any faults stored in the fault memory. Possible cause: Short to ground, main relay faulty Test precondition: EDC control unit connected Socked box connected Note:
Pin 46 must switch to U-Batt within 5 seconds of the ignition being switched off (processor run- on). 49 Test Measurement Corrective measures Main relay Measure voltage at socket box between pin 47 and pin 18 Set-point values: 0 V at “ignition” off U-Batt at “ignition” on Measure voltage at socket box between pin 46 and pin 18 Set-point values: U-Batt at “ignition” off 0 V at “ignition” on – Check lines – Check plug connections – If line OK, replace main relay