John Deere 700H Crawler Dozer — Assemble

Hydrostatic System NOTE: Apply clean hydrostatic oil to all internal parts prior to assembly. 1. Position shaft assembly (1) in housing (2). Align scribe mark between housing and flange (5). Install flange over shaft assembly as far as possible. Install two screws (M12 x 65 mm) 180 ° apart on flange. Alternately tighten screws until bottomed to seat flange and shaft assembly. Remove two 65 mm screws and repeat procedure using 50 mm screws. Remove screws. Install eight screws (4). Alternately tighten screws to seat shaft assembly and flange against housing. Torque screws to specification.

03 0360 52 Specification Flange-to-Motor Housing Cap Screw——Torque 110 (81 lb-ft) .......................................................... 1—Shaft Assembly 2—Housing 3—O-Ring 4—Screw (8 used) 5—Flange T8506AG –UN–30JUN95 TM1859 (14JUL04) 03-0360-52 700H Crawler Dozer Continued on next page CED,TX03399,5995 –19–14JUL04–2/9 071404 PN=242