John Deere 700H Crawler Dozer — Disassemble and Assemble Lift Section

Hydraulic System 8. Install detent spring (14) and ball cam (6). Hold detent balls (13) in place with grease. Slide spring collar (12) into place until it touches detent balls (13). Using a punch push through spring collar (12) into spool end and depress ball cam (6) against spring. This will allow balls (13) to retract so spring collar (12) can be moved fully into place. 10. Apply grease to spring (11). Install cap (7). 11. Install all remaining parts. Tighten cap screws (5 and 17) to specifications. Hydraulic Control Valve—Specification Lift Valve Spool Cap Socket Head Screws—Torque 9.5 ± 0.1 (84 ± 12 lb-in.) .........................

Lift Valve Retainer Plate Screws—Torque 5.5 ± 0.1 (48 ± 12 lb-in.) ................................... 9. Install parts (10, 11, 8 and 12) on spool. Clean threads of spool (19) and spool end (8) apply cure primer. Apply thread lock and sealer (high strength) on screw. Install and tighten to specifications. Hydraulic Control Valve—Specification Lift Valve Spool End Screw— Torque 9.5 ± 0.1 (84 ± 12 lb-in.) ................................................... CED,TX03399,6082 –19–31MAR00–2/2 32 3260 22 TM1859 (14JUL04) 32-3260-22 700H Crawler Dozer 071404 PN=574