Hitachi Construction Machinery — Main Pump Delivery Pressure

OPERATIONAL PERFORMANCE TEST / Component Test MAIN PUMP DELIVERY PRESSURE Preparation: 1. Stop the engine. 2. Push the air bleed valve on top of the hydraulic oil tank and release any remaining pressure. 3. Connect Dr. ZX and select the monitoring function. When Dr. ZX is not available, use the pressure gauge. Remove the plug of pressure check port from the main pump delivery port. Install adapter (ST 6069), hose (ST 6943) and pressure gauge (ST 6941). Main Pump 1 Side Plug : 6 mm 4. Start the engine. Confirm that no oil leakage is observed at the pressure gauge connection. 5. Maintain the hydraulic oil temperature at 50 ± 5 ° C (122 ± 41 ° F). Measurement: 1.

Measurement Conditions are below. T1J1-04-05-001 Main Pump 2 Side 2. Measure pressure with the control levers in neu- tral without load. 3. Repeat the measurement three times and calcu- late the average values. Evaluation: Refer to the Operational Performance Standard in Group T4-2. Remedy: Refer to the Troubleshooting B in Group T5-7. Plug T1J1-04-05-002 T4-5-6 Engine Control Dial Power Mode Switch Auto-Idle Switch Work Mode Fast Idle HP Mode OFF Digging Mode