MAINTENANCE EVERY 500 HOURS MAINTENANCE Maintenance for every 250 hours service should be carried out at the same time. LUBRICATING During the initial 50 hours breaking-in period for a new machine, carry out lubrication every 10 hours. If digging operations have been carried out in water (such as digging holes), always carry out greasing for the pins that were under water. For heavy-duty operations, such as hydraulic breaker work, carry out lubrication every 100 hours. 1. Set the machine to the greasing posture shown on the right, lower the work equipment to the ground, then stop the engine. 2. Using a grease pump, pump in grease through the grease fittings shown by arrows. 3.
After greasing, wipe off any old grease that was pushed out. (1) Boom cylinder rod pin (2 places) (2) Arm cylinder foot pin (1 place) (3) Boom-Arm coupling pin (1 place) (4) Arm cylinder rod end (1 place) (5) Bucket cylinder foot pin (1 place) (6) Boom cylinder foot pin (2 places) PC300LC/HD-7E0 3-51