4. After loading the rock completely into the bucket, operate the bucket tilt and lift two to three times repeatedly to fill the bucket. OPERATION 5. Let back the accelerator pedal; operate the control levers slowly; and tilt the bucket back fully. 6. To prevent the load from falling out of the bucket, after completing the scooping-up operation operate in the dump and tilt direction when the bucket is near the full tilt in order to stabilize the load. Remark If the brakes are operated lightly before traveling in reverse, it is possible to stabilize the load in the bucket.
To prevent generation of heat in the torque converter, keep the standard time for digging to within 10 seconds from the start of pushing the bucket in to the completion of scooping up. WA430-6 2-127