DOOSAN ŠKODA POWER — DOOSAN ŠKODA Power Steam Turbine Assembly Manual PDF (210 MW Bandel) (EN)

Instructions for ST assembly 210 MW Bandel India Document number: S12003-YK09-05MAA-747002 Tylova 57l 31600 Plzeň l Českб Republika DOOSAN SKODA POWER Tylova 1/57 301 28 Plzen Czech Republic Project manager: Ing. Petr Blecha telephone: + 420 37818 5576 email: petr.blecha@doosan.com Main project manager: Ing. Rudolf Vacovskэ telephone: +420 37818 5070 email: rudolf.vacovsky@doosan.com DOOSAN SKODA POWER Tylova 1/57 301 28 Plzeň Českб Republika Manažer projektu: Ing. Petr Blecha telefon: + 420 37818 5576 email: petr.blecha@doosan.com Hlavnн inženэr projektu: Ing. Rudolf Vacovskэ telefon: +420 37818 5070 email: rudolf.vacovsky@doosan.com Date: 12.11.2013 Page 8 / 278 Prepared:

O.Baroch Last Revision: Approved: P.Lešetickэ 1 Initial data / Úvodní informace 1.1 Identification of supplier / Identifikace dodavatele