XT855 Operator’s Manual Dig - 65 Digging p Digging Single Inline Trench 1. Position unit with tracks parallel with the intended digging path. 2. Fill and dump buckets. 3. Reposition unit as needed to continue trench. IMPORTANT: If operator is facing excavator when driving, unit movements are reversed. 4. When trench is finished, stow excavator, pivot seat to face tool carrier end, switch unit into tool carrier mode and drive away from trench. Single Offset Trench 1. Position unit near the intended digging path. 2. Swing excavator and offset boom as needed to align with digging path. 3. Fill and dump buckets. 4. Reposition unit as needed to continue trench. IMPORTANT:
If operator is facing excavator when driving, unit movements are reversed. 5. When trench is finished, stow excavator, pivot seat to face tool carrier end, switch unit into tool carrier mode and drive away from trench. CMW