Komatsu — 5.20. HOOD ASSEMBLY AND RADIATOR GRILL

SECTION 5 MAINTENANCE Page 54 5.20. HOOD ASSEMBLY AND RADIATOR GRILL Ample access to the engine compartment is provided by two side doors in 515C loaders. The doors are opened by pulling handles 1 and lifting the doors up. The doors are held in this position by two gas springs. Lubricate the gas spring seats and the door hinges periodically. Fig. 5.48. Hood Assembly (515C Loader) 1. Handle Bar The hood assembly can be swung back giving an easy access to the engine points in 520C. Release lever (2) and pull handle bar (1) back to open the hood assembly. Grease periodically hinge pins (3). 1 2 3 Fig. 5.48A. Hood Assembly (520C Loader) 1. Handle Bar 2. Lever 3.

Pins In CE version the side access doors can be opened by pulling latch handle (2) and swinging the door up and held in this position by gas springs. The radiator shield (1) can also be swung up. Grease periodically the spring seats, door hinges and hood pins. OM515C520C99/1E DRESSTA