Service - 76 SK600 Operator’s Manual Procedures Track Tension p Check before startup and every 10 hours. Adjust as needed. Check 1. Remove cover. 2. With tube and tab (top): Measure distance (A) from end of viewing window to front end of spring guide. Tension is correct when measurement is 5/8-3/4” (16-19mm). With mark on tube (bottom): Ensure mark on tube (2) is aligned with cutout (1) in plate. 3. Install cover. Adjust 1. Remove cover. 2. With tube and tab (top): Measure distance (A) from end of viewing window to front end of spring guide (orange tab). Tension is correct when measurement is 5/8-3/4” (16-19mm). With mark on tube (bottom):
Ensure mark on tube (2) is aligned with cutout (1) in plate. 3. Turn bolt (shown) clockwise to tighten and counterclockwise to loosen as needed. 4. Install cover. 2 1 25w.eps