hitachi — PREPARATION FOR PERFORMANCE TESTS

OPERATIONAL PERFORMANCE TEST / Component Test Measurement: 1. Measurement Conditions are below. 2. Slowly operate the bucket, arm and boom control levers to the stroke ends and relieve each func- tion. 3. Read pressures at this time. 4. Perform the measurement for the bucket, arm and boom in that order. 5. Repeat the measurement three times and calcu- late the average value for each. Evaluation: 1. Performance of the overload relief valves are normal if the measured main relief pressures are within the specified value range. Refer to the Performance Standard in Group T4-2. Overload Relief Valve Pressure Adjustment Pro- cedure NOTE:

In principle, adjust the overload relief valve pressure on a test stand. Loosen lock nut (1) and adjust pressure by using adjusting screw (2). 1. Loosen lock nut (1). : 19 mm 2. Turn adjusting screw (2) in order to adjust pres- sure. T162-04-04-004 : 6 mm 3. Tighten lock nut (1). : 19 mm 2 : 31.5 N m (3.2 kgf m, 23 lbf ft) 4. Check the set pressure. Pressure Decrease Pressure Increase W107-02-05-129 T4-5-13 Engine Control Dial Power Mode Switch Auto-Idle Switch Work Mode Fast Idle HP Mode OFF Digging Mode 1 2 1 NOTE: Standard Change in Pre Screw Turns 1/4 Change in Pressure MPa (kgf/cm2) (psi) 5.0 (51) (725)