SEN02738-00 50 Disassembly and assembly Replacement procedure for primary belt conveyor head pulley frame 1 a If the belt conveyor head pulley frame has been deformed or its parts have been removed, perform the following check and then adjust or replace the parts. 1. Rotate the belt conveyor. a Engine speed: High idle 4. Lower the conveyor assembly. (For removal, see "Removal and installation of primary belt conveyor".) 2. Visually check the frame for lateral swing (D). a If lateral swing is detected, replace the pulley frame according to the following procedure. Reference: If lateral swing is 3 mm or larger, it can be checked visually. 3.
Loosen tension adjustment bolt (1) to reduce the belt tension. a Loosen the tension adjustment bolts fully. a Make a mark at the original tension point in advance. a When replacing the frame without remov- ing the conveyor assembly, fix the head pulley according to the following steps 1) – 3). 22 BR380JG-1E0