Downloaded from https://www.everyspec.com MIL-HDBK-502: A MIL-HDBK-502: A CQUISITION CQUISITION L OGISTICS OGISTICS be adequately defined in Section B and the specification. SOWs or SOOs are usually prepared using the Work Breakdown Structure described in MIL-HDBK-881. Prior to acquisition reform, a SOW was written in a very prescriptive, task-oriented manner. Now under acquisition reform, the philosophy is for a SOW to be stated in performance terms (objectives or requirements) as much as possible. Other approaches are also being considered in upper levels within the Office of the Secretary of Defense.

These include issuing government-developed draft SOWs for contractors to respond to, or just providing a system specification or Operational Requirements Document without a SOW being utilized at all. Whatever approaches are deemed appropriate, it is apparent that the old way of writing SOWs will no longer suffice. Statement of Work The statement of work is the contractual vehicle for expressing what performance objectives or requirements a contractor must meet and the work the contractor is to perform. It is the keystone of the request for proposal (RFP), the offerors' proposals, and the resulting contract.

The statement of work may be incorporated directly into Section C or it may be included as an attachment to the contract and listed in Section J. The clarity of the statement of work has a direct effect on efficient contract administration because it defines the scope of work to be performed. Ambiguous statements of work, or statements of work with unduly restrictive requirements, result in unsatisfactory performance, delays, disputes, and higher costs. During proposal evaluation and source selection, the statement of work plays a significant role.

Failure to adequately describe the scope of work often results in needless delays and extra administration effort during the source selection process. The ability to clearly define the desired performance objectives or requirements of the end product in a clear, precise manner often affects the type of contract which will be selected. A well-defined product can often be acquired with a fixed-price contract; a product that cannot be defined precisely is usually acquired using a cost reimbursement contract. After contract award, the statement of work becomes the standard for measuring contractor performance.

As the effort progresses, both the government and the contractor constantly refer to the statement of work to determine their respective rights and obligations with regard to the contract. When a question arises concerning an apparent change in a performance requirement or an increase in the scope of work to be performed, the statement of work is the baseline document that must be used to resolve the issue. Language in the statement of work that defines the limits of the contractor's effort is of critical importance. If the limits are poorly established, it is difficult 8-8