GENERAL SPECIFICATIONS 1-8 E URO C ARGO E URO 4 - 5 1.11 Vehicle delivery Vehicle delivery Prior to delivering the vehicle, the body builder shall:
- verify that the work has been made correctly; - perform vehicle and/or equipment set-up; - check the operation and safety of the vehicle and/or equipment; - prepare and deliver the necessary instructions for service and maintenance of the fitting and any additional units to the end customer; - write the new data down on the special tags; - confirm that the work carried out complies with the indications provided by the vehicle manufacturer and with all the legal requirements for the country of registration; - carry out the checks included in the ”IVECO Pre-Delivery inspection” list (available from the IVECO network) with regard to the items affected by the work carried out; - provide a guarantee for the modifications made; - if for any reason bolted components have to be temporarily removed from the vehicle, when refitted new fixing hardware must be used.
When riveted components are removed these must be refitted using flanged head bolts and nuts. Use grade 10.9 hardware for high-stress components e.g. spring hanger brackets etc. The bolt torque must be checked after the vehicle has been driven approximately 500 to 1000km; - after 1 hour of the vehicles arrival check the battery charge status and enter the results on the Vehicle On-board Maintenance Form 1 Iveco Standards permit the following actions depending on the state of charge.
- Battery Charge Status ≥ 12.5v - Battery is OK - Battery Charge Status between 12.1v and 12.49v - battery requires slow charge - Battery Charge is lower than 12.1v then If Midtronics equipment is available ; - Verify Results and Test Code using the above equipment.
- If the Midtronics test and diagnosis results confirms then request a replacement battery from Iveco Warranty Department* - Otherwise follow the Midtronics diagnosis to recharge the battery or other actions If Midtronics equipment is not available - Request a replacement battery from Iveco Warranty Department * * Any requests for battery replacement must be certified by completion of the Battery Check Form, held by the bodybuilder and retained for the period of time as stated in the bodybuilders Quality Manual Procedures for document retention and be compliant with the ISO 9000/2000 Standard. Vehicle delivery Base - July 2006 Revi - June 2007 Print 603.93.431