SuperServer 1019P-WTR User's Manual Chapter 2: Server Installation Warning: Stability hazard. The rack stabilizing mechanism must be in place, or the rack must be bolted to the floor before you slide the unit out for servicing. Failure to stabilize the rack can cause the rack to tip over. Note: Figure is for illustrative purposes only. Always install servers to the bottom of a rack first. Installing the Chassis into a Telco Rack To install the chassis into a Telco or post-style rack, use two L-shaped brackets on either side of the chassis (four total). First, determine how far follow the server will extend out the front of the rack.
Larger chassis should be positioned to balance the weight between front and back. If a bezel is included on your server, remove it. Then attach the two front brackets to each side of the chassis, then the two rear brackets positioned with just enough space to accommodate the width of the telco rack. Finish by sliding the chassis into the rack and tightening the brackets to the rack. 2.4 Installing the Server into a Rack You should now have rails attached to both the chassis and the rack. The next step is to install the server into the rack. Installing the Chassis into a Rack 1. Confirm that chassis includes the inner rails and inner rail extensions.
Also confirm that the outer rails are installed on the rack. 2. Align the chassis inner rails with the front of the out rails on the rack. 3. Slide the chassis rails into the rack rails, keeping the pressure even on both sides (you may have to depress the locking tabs when inserting). When the server has been pushed completely into the rack, you should hear the locking tabs click into position. 4. (Optional) Insert and tighten the thumbscrews that hold the front of the server to the rack. Figure 2-4. Installing the Server into a Telco Rack Figure 2-3. Installing the Server into a Rack Note: Figure is for illustrative purposes only. Always install servers to the bottom of a rack first. 23 22