Downloaded from https://www.everyspec.com MIL-STD-1311C 31 January 2001 METHOD 5115 SHOCK (Cathode-ray tubes) 1. The test shall be performed in accordance with MIL-STD-202, method 213, table 213-1, test condition A. The following conditions apply: a. The tube shall be mounted to the elevator table by a suitable rigid assembly. Hardwood clamps shall be used at the face plate and near the neck to secure glass tubes (having no integral metal shields) to the assembly. Hardwood or metal clamps may be used at similarly appropriate points on tubes having integral shields. b. The assembly shall be such as to permit changes in tube orientation.
A total of 10 shocks shall be applied to the tube in the order, number, and directions as follows: Order Number of drops Direction 1 2 3 4 5 2 2 2 2 2 Base to face X+ X- Y+ Y- c. No potentials shall be applied during shock. 2. After shock test, cathode-ray tubes shall be subjected to the following tests and shall meet the requirements specified. a. The change in position of the undeflected focused spot from its position noted before the test (see method 5231) shall not exceed the following values: Tube face diameter or diagonal (in.) Change mm 1 2 3 4 5 and 6 7 and 8 9 10 and 11 12 and over 1.5 3 3 4 4 5 6 6 8 b.
The change in deflection factor for electrostatic tube types shall not exceed 5 percent (see method 5248). c. Starting with a tube with no loose particles, the maximum number of loose particles as a result of shocking shall be not more than a total of five loose particles greater than .016 inch (0.41 mm) in any one cathode-ray tube. Tubes having loose particles greater than .016 inch (0.41 mm) shall be vibrated with the face down in a horizontal plane at 5 G's for 1 minute. If the screen shows damage from such vibration, the tube shall be rejected. d. The change in grid cutoff voltage shall not exceed 10 percent (see method 5241). e.
There shall be no damage to the external parts of the tubes. METHOD 5115 19 April 1968 5115-1