E-l 1: INSTALLATION OF BOOM CYLINDER FOOT PIN 1. Raise the boom cylinder with a crane, align with the chassis pin holes, then push in the pins. & Boom cylinder assembly: 1300 kg & Inside of bushing: Anti-friction compound (LM-P) 2. Check the clearance (at the outside of the chassis) between the chassis and the end of the cylinder boss. Select a shim thickness to make the clearance 2 - 3 mm, and assemble the shims. Adjust both the chassis). left and right cylinders with shims. (Outside of 3. Push the boom foot pin in fully, then install the lock plate. 4. Install the left and right sides in the same way. * Assemble so that the boom cylinder bottom greas- ing hole is at the bottom.
* the adjustment shim. Combine the following shim thicknesses to make (%2lN-72-11230x8) tl.0 a P Shim Parts sent individually No. Part No. Part Name Q’ty II:--- 21 N 72-11230 ) (Shim tl.O) 1 8 2 21 N-63-3010 (Boom cylinder assembly) L.H. 1 3 21 N-63-3020 (Boom cylinder assembly) R.H. 1 115