3. To create room for installing the power take- off gear, move the KV/K1 clutch pack in the direction of the arrow. See Figure 4-250. packs, KV/K1 and KR/K2. See Figure 4-252. FIGURE 4-256 4694 FIGURE 4-253 4691 Install the gear so that the long collar faces down, toward the bearing. 6. Turn the transmission 180°. See Figure 4-253. To prevent any parts from falling off the clutch packs, hold the clutch packs from the rear. 4. Heat the ball bearing. Insert the PTO drive shaft through the gear and into the bearing. See Figure 4-251. Install the snap ring on the drive shaft. 7.

For each of the two clutch packs, install the FIGURE 4-257 4695 FIGURE 4-254 4692 split tab washer, grooved disc, and the shim washer that was calculated. See Figure 4- 254. Remove the dummy shafts from the clutch pack bores and install them into the 5. Install a dummy shaft into each of the clutch FIGURE 4-258 4696 FIGURE 4-255 4693 Mega 300-III Shop Manual TORQUE CONVERTER AND TRANSMISSION 4-65