9.4 CRANKING MOTOR 9.4.3 Installation of Cranking Motor Install the cranking motor as follows: ELECTRICAL SHOCK To avoid injury from electrical shock, follow OEM furnished operating instructions prior to usage. 1. Support the cranking motor, and install the three bolts that secure it to the flywheel housing. 2. Connect the cranking motor cables and the solenoid wiring. 3. Install the ground strap or negative cable(s) to the battery(s). 4. If an aluminum flywheel housing is used, torque the cranking motor attaching bolts to 187-209 N·m (138-154 lb·ft). If a cast iron flywheel housing is used, torque the cranking motor attaching bolts to 245-306 N·m (181-226 lb·ft). 5.

If equipped with a 42 MT or 50 MT starting motor, install wiring terminal leads to the cranking motor and the solenoid switch. 6. Torque the smaller connections to 1.8-3.4 N·m (16-30 lb· in.). Torque the larger connections to 27-34 N·m (20-25 lb·ft). NOTE: Keep all of the electrical connections clean and tight. 7. Refer to section 12.2 for verification of proper cranking motor installation. (Rev. 2005) All information subject to change without notice. 9-30 6SE483 0507 Copyright © 2005 DETROIT DIESEL CORPORATION