Komatsu — Specific Gravity Hydrometer Test

MAINTENANCE EVERY 2000 HOURS SERVICE _k Maintenance for every 50,100,250,500 and 1000 hours should be carried out at the same time. BATTERIES Check the batteries and mounting for defective cables, loose connections, loose or damaged hold down parts, damaged terminal posts, clogged vent holes, cracked, or distorted battery case or cover and accumulations of dirt, moisture and corrosion. Replace any damaged parts. If corrosion is found on the terminal posts, disconnect the cables from the battery, ground cable first, using the proper tools. A terminal cleaning brush can be used to clean tapered posts and the mating surfaces of the cable clamps.

The cable terminals should then be cleaned with an acid neutralizing solution of baking soda and water. Clean the dirt from the battery top with a cloth wetted with baking soda and water. Then wipe with a cloth with clear water. A wire brush can be used to remove dirt, corrosion or rust from the battery tray or hold down parts. After the tray and/or hold down parts are cleaned, rinse with clear water, dry with compressed air and repaint. After cleaning, reinstall the battery and hold down parts. Coat the battery and cable terminals with terminal grease, and connect the cables to the battery terminals. Connect ground cable last. IMPORTANT:

Frequent need for refilling battery cells may indicate that battery is being overcharged. Check charging system and voltage regulator as needed. A WARNING! When performing battery tests, observe the rules of safety. Always follow instructions of the test equipment manufacturer. STEP I -VISUAL INSPECTION 1. Visually inspect the outside of the battery for obvious damage such as cracked or broken case or cover which would allow electrolyte loss. Check for terminal damage. If obvious physical damage is found, replace the battery. If possible, determine the cause of damage and correct. 2. Check the electrolyte level. 3.

If the electrolyte level is above the separator plates in all cells, proceed to Step II. 4. If the electrolyte level is below the tops of the separator plates in one or more cells, add distilled water until the electrolyte level is at the level indicator or 13 mm (l/2 in) above the tops of the separator plates. 5. Then charge the battery for 15 minutes at 15-25 amperes to mix the water with the electrolyte. After mixing electrolyte proceed to Step II. STEP II - STATE OF CHARGE TEST The battery’s state of charge can be determined by either the specific gravity hydrometer test or by the stabilized open circuit voltage test. Specific Gravity Hydrometer Test NOTE:

If necessary, refer to the instructions for reading a hydrometer. 3-68