Case IH AFX8010 — CLEANING Primary cleaning

CROP PROCESSING - CLEANING Primary cleaning Upper sieve drive system - Install (K.62.B.42 - F.10.A.15) AFX8010 1. Press the new bushing (1) onto the pin (2) until the center metal insert of the bushing is flush plus or minus +/- .5 mm (+/- 0.020") with the top pin. 40015727 1 2. Install the bushing assembly with the previously removed cap screw at (1) . Torque the cap screw to 150 - 170 Nm(111 - 125 lb ft) . 40015719 2 3. Rotate the leveling frame to make the appropriate side accessible. Install the arm clamp (1) onto the bushing. 50013948a 3 4. Do not tighten the hardware until instructed. NOTE: a spacer is to be installed between the drive arm and clamp at (2) .

9717 1 27/05/2004 K.62.B / 26