Hyundai Construction Equipment — 1. OPERATIONAL PERFORMANCE TEST

Unit : mm / 20 m 7-7 5) TRAVEL DEVIATION (1) Measure the deviation by the tracks from a 20m straight line. (2) Preparation 刮 Adjust the tension of both tracks to be equal. 刯 Provide a flat, solid test yard 20 m in length, with extra length of 3 to 5 m on both ends for machine acceleration and deceleration. 到 Hold the bucket 0.3 to 0.5 m above the ground with the arm and bucket rolled in. 刱 Keep the hydraulic oil temperature at 50佳5˚C. (3) Measurement 刮Measure the amount of mistracking at high and low travel speeds. 刯Before beginning each test, select the following switch positions. 余Power mode switch :

M mode 到Start traveling the machine in the acceleration zone with the travel levers at full stroke. 刱Measure the distance between a straight 20 m line and the track made by the machine. (Dimension a) 刲After measuring the tracking in forward travel, turn the upperstructure 180佘and measure that in reverse travel. 刳Repeat steps 刱 and 刲 three times and calculate the average values. (4)Evaluation 0.3~0.5m 21097MS04 3~5 m extra length a 20M 3~5 m extra length (210-7) 7-7(2) 0.3~0.5m 21097MS04 Mistrack should be within the following spe cifications. Model Standard Maximum allowa ble Remarks 210HD, HX220HD 200 below 240