Komatsu — V-SHAPED LOADING TECHNIQUE

7. If there is too much material in the bucket, tip the bucket forward slightly to dump excess material then tilt it back when the load is ready to transport. OPTIONAL ATTACHMENTS Remark Be careful not to get blasted rock under the bucket. This will cause the front tires come off the ground and slip. Try to keep the load in the center of the bucket; if the load is on one side of the bucket, the load will be unbalanced. LOAD AND CARRY OPERATIONS When carrying a load, keep the bucket as low as possible to lower the center of gravity when traveling. When the machine is traveling or the work equipment is raised, and the E.C.S.S. switch is turned ON , the work equipment will move.

If operations are carried out with the E.C.S.S. switch in the ON position, and the travel damper is actuated, the work equipment will also move. The load and carry method for wheel loaders consists of the cycle of scooping - hauling -loading (into a hopper, truck, etc.) Always keep the travel path properly maintained. LOADING TRUCKS OR HOPPERS Select the method of operation which will give you the minimum amount of turning and travel in order to provide the most efficient method for the job site. Always set the wheel loader facing at a right angle to the stock pile.

After scooping up the load, drive the machine straight back in reverse, then bring the dump truck in between the stock pile and the wheel loader. This method requires the least time for loading, and is extremely effective in reducing the cycle time. V-SHAPED LOADING TE CHNIQUE Position the dump truck so that the direction of approach of the wheel loader is approx. 60 degrees from the direction of approach to the stockpile. After loading the bucket, drive the wheel loader in reverse, then turn it to face the dump truck and travel forward to load the dump truck. The smaller the turning angle of the wheel loader is, the more efficient the operation becomes.

When loading with a full bucket and raising it to the maximum height, first shake the bucket to stabilize the load before raising the bucket. This will prevent the load from spilling to the rear onto the machine. WA320PT-5L 5-5