Kaiyi — 4. MECHATRONICS SYSTEM

2) TEST PROCEDURE (1) Test 1 : Check resistance at connector CN-75. Starting switch OFF. Disconnect connector CN-75 from EPPR valve at main hydraulic pump. Check resistance between 2 lines as figure. SPEC : 15~25 Ω (20 C) CN-75 ① ② EPPR valve ③ Multimeter Main pump 900L6MS02 (2) Test 2 : Check electric current at EPPR valve. Disconnect connector CN-75 from EPPR valve. Insert the adapter to CN-75 and install multimeter as figure. Start engine. Set S-mode and cancel auto decel mode. Position the multimodal dial at 10. If tachometer show approx 1650 ± 50 rpm disconnect one wire harness from EPPR valve. Check electric current at bucket circuit relief position. ① ② ③ ④ ⑤ ⑥ ⑦ (3) ① Test 3 :

Check pressure at EPPR valve. Remove plug and connect pressure gauge as figure. Spec : 2~25 kgf/cm 2 (30~350 psi ) Pressure adjusting screw locknut · Gauge capacity : 0 to 50 kgf/cm 2 ② ③ (0 to 725 psi ) Start engine. Set S-mode and cancel auto decel mode. Position the multimodal dial at 10. If tachometer show approx 1650 ± 50 rpm check pressure at relief position of bucket circuit by operating bucket control lever. If pressure is not correct, adjust it. After adjust, test the machine. ④ ⑤ EPPR valve Pilot pressure supply line ⑥ ⑦ 900L5MS22 6-41 Spec : 100~700 mA Adapter(P/no.:21Q6-50410) CN-75 EPPR valve Multimeter Main pump 900L5MS21