Hydraulic System TM1859 (14JUL04) 32-3260-9 700H Crawler Dozer 071404 PN=561 Disassemble and Assemble Hydraulic Control Valve IMPORTANT: Keep all components for each valve section together as a set. –UN–19JUL00 1. To aid in assembly, identify each section with a mark. 2. Remove nuts (1). T132579 3. Place valve in a vertical position having the inlet section down and supported by wood blocks. 4. Remove tie rods (2). 5. Carefully remove sections (3—8) so as not to lose or damage O-rings (11), load checks (10), and springs (9). Keep load checks and valve sections together as a set. IMPORTANT: Use care not to damage or score mating surfaces of valve sections. 6.
Inspect O-rings between each section for wear or damage. Replace as necessary. 7. Inspect springs and load checks for scoring, wear, or N–22JAN99 damage. Replace as necessary. 8. Apply clean hydraulic oil to all internal parts. –U T119779 9. Install load check, spring, and O-ring into each spool section. 1—Nut (6 used) 10. Assemble sections (3—8), making sure load checks, 2—Control Valve Tie Rod (3 used) springs, and O-rings remain in position. 3—Inlet Valve Cover 4—Auxiliary Valve Section IMPORTANT: Tighten tie rod and nuts evenly to 5—Blade Angle Valve Section prevent valve spool binding or leakage 6—Blade Tilt Valve Section 7—Blade Lift Valve Section between sections.
8—Outlet Valve Cover 9—Spring (1 in each spool section) 11. Tighten tie rod nuts (1) to specifications. 10—Load Check (1 in each spool section) 11—O-Ring (1 between each section) Hydraulic Control Valve—Specification Control Valve Assembly 7/16-20 in. Tie Rod Nuts—Torque............................. 65 ± 5 N•m (576 ± 42 lb-in.) Control Valve Assembly 1/2-20 in. Tie Rod Nuts—Torque................................ 100 ± 6 N•m (888 ± 60 lb-in.) CED,TX03399,6077 –19–31MAR00–1/1 32 3260 9