Komatsu — DISASSEMBLY OF 1 LINK IN THE FIELD

DISASSEMBLY AND ASSEMBLY TRACK SHOE 2. Set the link (3) to which link sub-assembly will be connected. 3) Operate lever block [2] to align the link hole and bushing hole, and then connect the link with guide R2-11 . 3. Set link (4) on the opposite side and support it with tool R2-10 . 4) After connecting the link with guide R2-11 , remove jack R2-7 . 4. Set tool R2 as in the procedure for removing the pin. Using tool R2-1 , press fit the pin to link sub- assembly (5). a Pressing force for ping: 206 – 255 kN {21 – 26 tons} 6. Press fitting of pin 1) Using screw R2-4 and nut R2-3 , install frame R2-1 to the cylinder. 2) Using the screw, install adapter R2-5 to frame R2-1 .

3) Set extension R2-2 and press fit pin (6). a Set the pin with its side hole directed toward the tread of the link. a Pressing force for ping: 412 – 510 kN {42 – 52 tons} 5. Connection of link 1) Set lever block [2]. 2) Install jack R2-7 and spacer [1] on the tread side of the link and apply hydraulic pressure to the jack until the link tip opens by 6 – 8 mm. D85EX-15 30-165 (2)