Komatsu D155AX-6 — EMERGENCY OPERATION METHOD WHEN WORK EQUIPMENT HAS TROUBLE

30 Testing and adjusting SEN00680-01 6. Disconnect EPC solenoid connectors EWP1 WEPA above the control valve and connect connectors WEPX and WEPY of wiring har- ness T to the male side. a Disconnect only the pair (2 pieces) of the connector of the control valve spool (cylin- der) to be moved and connect the connec- tors on the wiring harness T side to them respectively. a When connecting the connectors, check the operating direction of the switch and the connector numbers again. 7. Start the engine and operate switch [1] of wir- ing harness T to move the work equipment. k Before starting the engine, check that the switch is in neutral.

k Since the work equipment cannot be controlled finely with the switch, keep the engine speed as low as possible. k Do not connect wiring harness T to the HSS connectors (HSL and HSR). 8. After finishing operation of the work equip- ment, remove the tools used and return the removed parts. a Connectors to be connected (The follow- ing table is for the dual tilt specification. WEP5 and WEP6 are not connected to the single tilt specification.) D155AX-6 29 Connectors on machine side Device/Operating direction No.

Band color Raise Blade lift Lower WEP1 Green WEP2 Green/Black Retract Blade tilt left Extend WEP3 Brown WEP4 Brown/Black Retract Blade tilt right Extend WEP5 Blue WEP6 Blue/Black Raise Ripper lift Lower WEP7 Yellow WEP8 Yellow/Black In Ripper tilt Back WEP9 Red WEPA Red/Black Connectors on wiring harness T side Device/Operating direction No. Band color UP LIFT DOWN WEPX — WEPY —