Instructions for ST assembly 210 MW Bandel India Document number: S12003-YK09-05MAA-747002 Tylova 57l 31600 Plzeň l Českб Republika § Moving of bottom HP casing in closed forme onto the front HP and rear HP bearing stands. § Earthing of HP casing. § Levelling of HP casing and its attachment to the bearing stands. § Moving of bottom IP casing onto the rear HP bearing stand and on the LP casing. § Earthing of IP casing. § Levelling of IP casing and its attachment to the bearing stands. § Dismantling of the manoeuvre equipment including the supporting structures. 6) Assembly of cover of LP outer casing § Moving of the components of cover of LP outer casing onto bottom part.
Assembly of the cover together including the checking of contact among components in parting planes. § Erection of scaffolding in necessary range carrying out of the tightness welds. Dismantling of the scaffolding. § Moving of the cover on the bottom part and checking of contact in horizontal parting plane. Moving the cover aside onto wooden supports in accordance with drawing “Lay -down plan Pt6005538. 7) Assembly of LP inner parts into turbine § Z avezenн VT tělesa v uzavřenйm stavu na přednн VT a VT zadnн ložiskovэ stojan . § Uzemněnн VT tělesa . § V yrovnбnн VT tělesa a jeho upevněnн k ložiskovэm stojanům. § Zavezenн spodku ST tělesa na zadnн VT ložiskovэ stojan a NT těleso .
§ Uzemněnн ST tělesa . § V yrovnбnн ST tělesa a jeho upevněnн k ložiskovэm stojanům. § Demontбž manйvrovacнho zařнzenн včetně podpěrnэch konstrukcн. 6) Montбž vнka NT vnějšнho tělesa § Zavezenн dнlů vнk a NT vnějšнh o těles a na spodek . Smontovбnн vнka včetně kontroly dosedбnн dнlů v dělнcнch rovinбch. § Montбž lešenн v potřebnйm rozsahu, p rovedenн těstnostnнch svarů. Demontбž lešenн. § Zavezenн vнka na spodek a kontro la dosedбnн horizontбlnн dělнсн roviny. Odloženн vнka n a dřevěnй podložky dle vэkresu „Odklбdacн plбn“ Pt6005538. 7) Montбž NT vnitřnнch dнlů do spodku bottom parts and leveling § Gradually unpacking of bottom inner parts (, diaphragms, gland bodies, deflectors).
§ Assembly of the bottom and top halves of deflectors. § Hanging of the bottom halves of deflectors into the bottom part of LP outer casing. § Assembly of feathers and set-wedges into the bottom of LP outer casing. § Preparation of LP inner casing for the diaphragm inserting (preservation washing, turbiny a jejich vyrovnбnн § Postupnй vybalenн spodků vnitřnнch dнlů ( rozvбděсн kola, tělesa ucpбvek , deflektory) § Sestavenн hornнch a spodnнch polovin deflektorů § Zavěšenн spodnнch polovin deflektorů do spodku NT vnějšнho tělesa § Montбž per a stavěcнch klнnů do spodku NT vnějšнho tělesa § Přнprava střednнho NT tělesa pro vloženн rozvбděcнch kol (mytн konzervace, Date:
12.11.2013 Page 106 / 278 Prepared: O.Baroch Last Revision: Approved: P.Lešetickэ manévrovacího zařízení. § Zajištění opatření BOZP pro manipulaci s nadměrně hmotnými díly (zamezení vstupu osob, lokální přerušení montážních prací ve strojovně). § Providing of OHS measures for handling with abnormal-load components (preventing of entry of people, local interruption of assembly works in machine hall). § Assembly of walk-able platforms around the parting plane of turbine casings (handrails, earthing) § Montáž pochozích plošin okolo dělící roviny těles turbiny (zábradlí, uzemnění).
§ Creating of preassembly workplace for the tightness welds doing on cover of LP outer casing including adequate measures OHS, FP, EP (enough loading capacity of floor, ventilation, heating, inlet of electricity). § Vytvoření předmontážního pracoviště pro svařování těstnostních svarů na víku NT vnějšího tělesa včetně zajištění přiměřených opatření BOZP, PO a OŽP (dostatečná nosnost podlaží, odsávání, vytápění, přívod elektřiny).