Doosan DX225LC-3 — Track Tension

TRACK TENSION WARNING AVOID DEATH OR SERIOUS INJURY Measurement of track tension requires two people. Always follow these instructions: One person must be in the operator's seat running the controls to keep one side frame in the air, while the other person makes dimensional checks. Take all necessary precautions to make sure the machine does not move or shift position during service. Warm up the engine to prevent stalls. Position excavator in an area that provides level, uniform ground support and/or use support blocks when necessary. The track adjusting mechanism is under very high-pressure. NEVER release pressure too suddenly.

The track tension grease valve should never be backed off more than one (1) complete turn from the fully tightened down position. Bleed off pressure slowly and keep your body away from the valve at all times. Track shoe link pins and bushings wear with normal usage, reducing track tension. Periodic adjustment is necessary to compensate for wear and it may also be required by working conditions. 1. Track tension is checked by jacking up one side of the excavator. See Figure 163. Place blocking under frame while taking measurement. Turn the track backward 1 - 2 turns. 90 - 110 Figure 163 EX1300534 DX225LC-3 Inspection, Maintenance and Adjustment 4-100