hitachi — PREPARATION FOR PERFORMANCE TESTS

OPERATIONAL PERFORMANCE TEST / Component Test Evaluation: Convert the measured flow rates to those at the specified pump speed by using the following for- mulas: 2. Standard Flow Rate Refer to Operational Performance Standard in Group T4-2. Qc = (Np Ч Q) (Ne Ч i) Qc : Converted Flow Rate Q : Measured Flow Rate Np : Specified Pump Speed:1750 min -1 Ne : Measured Engine Speed : Values indicated on Dr. ZX i : Pump Speed Ratio:

1.0 1, 2 3 4 5 6 8 9 7 10 11 Delivery Hose (To Control Valve) T173-04-04-002 Fan Pump 14 T1JB-04-05-006 1 - Pipe E (ST 6144) 5 - Hydraulic Tester (ST 6299) 9 - Flange (ST 6118) 12 - Port Pr 2 - Pipe B (ST 6143) 6 - Adapter PF1 Ч UNF1-7/8 (ST 6146) 10 - Split Flange (ST 6130) 13 - Plug 12 13 3 - Test Hose (ST 6145) 7 - Joint (ST 6330) 11 - Bolt (ST 6409) (4 Used) 14 - Hose (ST 6339) 4 - Adapter PF1 Ч UNF1-7/8 (ST 6146) 8 - Test Hose (ST 6320) T4-5-17