OPERATIONAL PERFORMANCE TEST / Excavator Test MISTRACK CHECK Summary: 1. Allow the machine to travel 20 m (65.6 ft). Meas- ure the maximum tread deviation from the tread chord line drawn between the travel start and end points to check the performance equilibrium be- tween both sides of the travel device systems (from the main pump to the travel motor). 2. If measured on a concrete surface, the tread de- viation has a trend to decrease. Preparation: 1. Adjust the track sag of both tracks to be equal. 2. Provide a flat, solid test yard 20 m (65.6 ft) in length, with extra length of 3 to 5 m (9.8 to 16 ft) on both ends for machine acceleration and de- celeration. IMPORTANT:
The bucket teeth will hit the boom if the bucket is rolled-in with the arm fully rolled-in. As for this condition: arm fully rolled-in + Bucket fully rolled-in, set the bucket at fully rolled-in and a perform arm roll-in operation. 3. Hold the bucket 0.3 to 0.5 m (12 to 20 in) above the ground with the arm and bucket rolled in. 4. Maintain the hydraulic oil temperature at 50 ± 5 ° C (122 ± 41 ° F). Measurement: 1. Measure the amount of mistracking in both fast, and slow travel speeds. 2. Measurement conditions are as below. Evaluation: Refer to the Performance Standard Table in Group T4-2. Remedy: Refer to the Troubleshooting B in Group T5-7. Maximum Distance Acceleration Zone:
3 to 5 m 20 m T105-06-03-022 3. Start traveling the machine in the acceleration zone with the travel levers at full stroke. 4. Measure the maximum distance between a straight 20 m (65.6 ft) tread chord line and the tread made by the machine. 5. After measuring the tracking in forward travel, turn the upperstructure 180 ° and measure in re- verse travel. 6. Perform the measurement three times and cal- culate the average values. T4-4-3 Travel Mode Switch Engine Control Dial Power Mode Switch Work Mode Auto-Idle Switch Slow Mode Fast Idle HP Mode Digging Mode OFF Fast Mode Fast Idle HP Mode Digging Mode OFF