Komatsu — 20-201--.pdf

TESTING AND ADJUSTING TESTING AND ADJUSTING OIL PRESSURE IN WORK EQUIPMENT, SWING, AND TRAVEL CIRCUITS 3. Measuring work equipment circuit relief pres- sure 1) Start the engine and move the cylinder to be measured to the stroke end. 2) Run the engine at high idling and relieve the cylinder and measure the oil pressure. a The pressure measured when the main relief valve is relieved is indicated. a If the one-touch power maximizing switch is released, the main relief valve is relieved at low pressure. If the former is pressed, the latter is relieved at high pressure.

a If the swing lock switch is set in the LOCK position, the 2-stage relief solenoid valve is turned ON and the main relief valve is relieved at high pressure. Accordingly, keep the swing lock switch turned OFF. ADJUSTING a The unload valve cannot be adjusted. 1. Adjusting main relief pressure (High pres- sure setting side) a If the high relief pressure of the work equip- ment circuit and travel circuit is abnormal, adjust the high pressure setting side of main relief valve (2) according to the following pro- cedure. a The high relief pressure is the pressure applied when the 2-stage relief solenoid valve is turned ON and the pilot pressure is applied to the selector port. 4.

Measuring swing circuit relief pressure 1) Start the engine and set the swing lock switch in the LOCK position. 2) Run the engine at high idling and relieve the swing circuit and measure the oil pressure. a The pressure measured when the swing motor safety valve is relieved is indicated. a The swing motor relief pressure is lower than the main relief pressure. 5. Measuring travel circuit relief pressure 1) Start the engine and lock the travel mecha- nism. 1) Disconnect pilot hose (3). 2) Fixing holder (4), loosen locknut (5). 3) Turn holder (4) to adjust the pressure. a If the holder is turned to the right, the pressure rises. turned to the left, the pressure low- ers.

a Quantity of adjustment per turn of holder: Approx. 12.6 MPa {Approx. 128 kg/cm 2 } 4) Fixing holder (4), tighten locknut (5). k Set pin [2] between the sprocket and track frame to lock the travel mecha- nism securely. 3 Locknut: 39.2 – 49 Nm {4 – 5 kgm} 2) Run the engine at high idling and relieve the travel circuit and measure the oil pressure. a The pressure measured when the main relief valve is relieved is indicated. The travel cir- cuit is always relieved at high pressure. 5) Connect pilot hose (3). PC130-7 20-123 (1)