Komatsu — OPERATING METHOD FOR RIPPING OPERATIONS

. OPERATION OPERATION DIGGING UP BOULDERS lever to the TILT position and carry out 3 - 154 During the rip ping operation, if boulders are fou nd which are difficult to break and shoe slip page occurs, dig up t he boulder as fo 1. Depress the decelerator p edal and l ower th e engine speed to a point w here there i s no s hoe 2. Operate the ripper l ripping a nd digging. 3. If there a re boulders whic h are impossible to break or dig up with the t ilt operation , mov e forward slightly and tilt t he shank back, the n operate t he tilt again and dig up the boulder. 4.

Even wh en the op eratio n in Ste p 3 is repeate d, i f it is impossib le to break or dig up th e boulder, d rive back about 10 cm, raise the shank, avoid the rock or boul der that cannot be ripped, th en drive for ward and s tart ripping again.