Downloaded from https://www.everyspec.com MIL-HDBK-704-3 5. Compliance test. With the power source off, install the UUT and the stimulation and monitoring equipment into the test setup of figure TAC302-1. Turn on the power source and adjust the voltage to the nominal steady state voltage of 115 Vrms (line-to-neutral) and adjust the frequency to the nominal steady state frequency of 400 Hz. Energize the UUT. Allow sufficient time for the UUT to warm up. Conduct a performance test of the UUT according to the utilization equipment performance test procedures to verify that the UUT is providing specified performance for normal aircraft electrical conditions. 5.1 Compliance test for MIL-STD-704A.

The UUT must be subjected to the voltage transients for each test condition A through O noted in table TAC302-II. The voltage must increase or decrease from steady state voltage to the voltage transient level within Ѕ cycle (1.25 milliseconds). The voltage must remain at the voltage transient level for the duration noted in table TAC302-II. The voltage must return to steady state over the time duration noted in table TAC302-II. For test condition G, three over-voltage transients of 180 Vrms for 20 milliseconds are performed, separated by 0.5 seconds. For test condition N, three under-voltage transients of 45 Vrms for 20 milliseconds are performed, separated by 0.5 seconds.

For test condition O, an under-voltage transient of 45 Vrms for 20 milliseconds is immediately followed by an overvoltage transient of 180 Vrms for 75 milliseconds and the voltage returns to steady state over the time duration noted. For each test condition, monitor the performance of the UUT during the voltage transient according to the equipment performance test procedures to verify that the UUT is providing specified performance for abnormal aircraft electrical conditions. Repeat each test condition 5 times.

After the power returns to normal limits, conduct a performance test of the UUT according to the utilization equipment performance test procedures to verify that the UUT automatically returns to specified performance for normal aircraft electrical conditions when the power returns to within normal limits, and has not suffered damage. Record the steady state voltages, steady state frequency, voltage transient level, time duration at voltage transient, oscilloscope trace, and the performance of the UUT for each test condition in the data sheet shown in table TAC302-IV. Repeat for each mode of operation of the UUT. 5.2 Compliance test for MIL-STD-704B, C, D, E, & F.

The UUT must be subjected to the voltage transients for each test condition AA through OO noted in table TAC302-III. The voltage must increase or decrease from steady state voltage to the voltage transient level within Ѕ cycle (1.25 milliseconds). The voltage must remain at the voltage transient level for the duration noted in table TAC302-III. The voltage must return to steady state over the time duration noted in table TAC303-III. For test condition GG, three over-voltage transients of 180 Vrms for 20 milliseconds are performed, separated by 0.5 seconds. For test condition NN, three under-voltage transients of 45 Vrms for 20 milliseconds are performed, separated by 0.5 seconds.

For test condition OO, an under-voltage transient of 45 Vrms for 20 milliseconds is immediately followed by an overvoltage transient of 180 Vrms for 50 milliseconds and the voltage returns to steady state over the time duration noted. For each test condition, monitor the performance of the UUT during the voltage transient according to the equipment performance test procedures to verify that the UUT is providing specified performance for abnormal aircraft electrical conditions. Repeat each test condition 5 times. After the power returns to normal limits, conduct a performance test of the UUT according to the utilization equipment performance test 84