Downloaded from https://www.everyspec.com MIL-HDBK-683(AT) FKRA is required in an excellent tool for design and reliability review and should be conjunction with reliability testing. 4.5.6.1 ~- The procedure for conducting FMRA is as follows: Detemine potential failure modes. This is clearly the most diff;~lt step in the procees and relies on engineering experience and historical data taken from other products or previous designs. It is necessary to consider what could go wrong with the part or assembly and what symptam or effects on the product would be obsemmd. For example, in analyzing a radio, one potential failure mode would be that the speaker connection breaks.

The effect of this failure would be--no sound. b. Detemine the most likely cause for each of the failure modes to be addreaaed. Any of the problem solving techniques discussed in problem analysis and solution may be applied at this point. There may be more than one cause for a given failure mode- Estimate a probability of occurrence for each failure mode. To simp;~fy this estimate, use a scale of 1 to 10 to indicate probability with 1 being a ve~ luw probability and 10 being the highest probability of occumence. d. Eat&te the relative weight or criticality of each failure mode.

It is important to consider safety, conformance to specification, product function and customer satisfaction when assigning a relative weight. The same scale of 1 to 10 is used with 1 being an incidental failure that is unlikely to affect product performance or the customer-s perception of quality, and 10 being a critical failure that will cause personal injury or certain product failure. e. scale. rated 1 from an Estimate the probability of escaped defects, again using the 1 to 10 A perfect inspection station would catch all the defects and would be (low probability of esca~d defects). ThiB eBtimate may be derived Inspection Capability Study for a similar part.

Calculate a risk priority number multiplying the factors determined in Steps b, c, and d. The higher the risk priority nunber, the more ~rwt it will be to find a cause and preventive action. f. g- Identify appropriate preventive action that will eliminate the cause of the potential failure rode. Needless to say, the problem with the highest risk ~iority number should be worked on first. 4.5-6-2 ~. ~efoll~ingia ~ezle of how to conduct a FMRA using the above procedure. For this purpose, the FMRA worksheet (figure 7-4) is used to describe the project and to record the results of the Zwvim. a. The project in this example is to design an automatic umbrella.

In the upper section of the worksheet, the part number and description of the item, the name of the engineer and date of the project will be noted. 24