Downloaded from https://www.everyspec.com TOP 1-2-622 11 September 2009 Figure 2. Patuxent River VPD Facility. The Test Officer (TO) must ensure that the VEMP test facility utilized is the foremost facility to accurately simulate desired criteria and test system response in order to adequately test the system configuration. It is emphasized that available facilities will provide only a simulated VEMP environment. Therefore, in addition to good test data, adequate analysis must be performed to account for the facility deficiencies which must be known, quantified, and documented. 2.2 Instrumentation.
Devices for Measuring Permissible Measurement Uncertainty VEMP Environmental E-Field 2 kV/m or ±5 % (whichever is greater) VEMP Environmental H-Field 5 Ampere-Turns/Meter or ±5 % (whichever is greater) Current Amperes ±5 % Examples of acceptable instrumentation are shown in Table 2.2 on the preceding page. 4