Downloaded from https://www.everyspec.com TOP 1-2-622 11 September 2009 The TO must thoroughly understand the operation of all mission essential functions, test criteria, test facility limitations, test objectives, operational and maintenance procedures, performance and operational checkouts, material composition, instrumentation, system integration, environmental considerations, induced current analyses, statistical processes, and safety considerations to adequately devise a realistic test scenario, test schedule, and performance analysis program. 3.1.2 Cost Estimates.
Upon devising an appropriate test scenario, a Developmental Test Command (DTC) cost estimate must be prepared in accordance with (IAW) DTC Pamphlet 73-1 5 , Developmental Test Guide. The TO must ensure that the cost estimate adequately accounts for all reasonable expenditures of the proposed VEMP test and analysis program. These direct expenditures are for man-hours, material and supplies, travel, contractual service, equipment, minor construction, facilities, repair and replacement of test related consumables. IAW the National Defense Authorization Act 2003, only direct expenditures can be charged to DoD or DoD sponsored customers.
Additionally, these cost estimates must be posted in the U.S. Army Test and Evaluation Command (ATEC) Decision Support System (ADSS) and Vision Digital Library (VDL). 3.1.3 Test Coordination. From the initiation to the completion of the test program, test coordination is a constant and essential task. The TO must coordinate effectively with a multitude of various personnel in order to properly plan, resource, execute, and determine the VEMP survivability of a test system.
Without proper and effective test coordination, a VEMP System Test and Assessment (STA) program will experience cost overruns, unnecessary test delays, inadequate test data, improper determinations, and improper usage of manpower. In conclusion, test coordination is one of the most important aspects to a TO and is essential to the conduct of a successful program. 3.1.4 Environmental Impact. An important pretest requirement IAW AR 200-1, Environmental Protection and Enhancement 6 , and AR 200-2, Environmental Effects of Army Actions 7 , is an environmental analysis.
This analysis will help alleviate environmental problems that could interfere with the test schedule and completion of the VEMP STA program. The proper system under test (SUT) documents must be completed and submitted to the environmental office and/or personnel who regulate and control environmental practices at the test execution site prior to start-of-test. The actual time requirement for document submission before test execution is dependent on the level of preparation required, type of system, and required documentation as well as the workload of the environmental office. Most of the required information can be obtained from the Project Manager’s (PM's) office.
Facility and test location specific environmental documents should be provided by the test facility. 6